AMEY AUSTRALIAformerly Premise

Project 48 · Water

Motukea International Port Facility

We were engaged to provide design services to Curtain Bros (PNG) for a Design and Construct project for PNG Ports.

The project includes the construction of an international wharf facility and laydown areas, to accommodate the relocation of the existing Port facilities in Port Moresby.

To date, our team has provided: Concept design and documentation

Reclamation design Preliminary services design and documentation

The project will facilitate the relocation of the existing Port facility within downtown Port Moresby to Motukea Island, on the outskirts of the National Capital District.

Once vacated, the current Port site will provide strategic land and opportunities for extensive water front redevelopment and revitalisation of the city.

In this regard, our civil infrastructure design services encompass:

Design of causeway and road access to the proposed facility, including drainage culverts, services, and rock revetment

Design of reclamation works for approximately 10ha of land

Coastal engineering studies, and design of rock protection for the reclamation land

Internal access roads, stormwater drainage for the entire site, water supply and reticulation, electrical reticulation, lighting, communications, and sewage reticulation for the site

Secure fencing of the site